Risberg Pipeline Brings Natural Gas to Region
Source: Star Beacon Originally Posted on July 25th, 2020 by BRIAN HAYTCHER NORTH KINGSVILLE — In December of 2019, a group of elected officials, business leaders and construction workers gathered for the ribbon-cutting ceremony of a natural gas pipeline that runs from...
Conneaut’s Two Taps on the Risberg Pipeline Being Drafted
Source: Star Beacon Originally Posted on January 8th, 2020 by BRIAN HAYTCHER A request for proposals for the city’s two taps on the Risberg Pipeline is being drafted. The city has a pair of taps on the Risberg Pipeline, a natural gas pipeline running from Meadville,...
Natural Gas to Impact Ashtabula County Economy
Source: Star Beacon Originally Posted on January 5th, 2020 by BRIAN HAYTCHER Natural gas has started flowing in quantities into Ashtabula County, and it is poised to have an impact on the local economy. The Risberg Pipeline had a ribbon cutting in December, marking a...
Natural Gas Flows into Ohio
Source: Star Beacon Originally Posted on December 14th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE — Dozens of people gathered in North Kingsville on Friday to celebrate the ribbon cutting for a new natural gas pipeline. Seven people cut the ribbon on the Risberg...
Testing Nears Completion on Meadville-to-Ohio Pipeline
Source: Meadville Tribune Originally Posted on November 14th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE, Ohio — Testing has finished on the Ohio portion of a new natural gas pipeline. The testing process has moved on to the Pennsylvania section of the Risberg pipeline,...
Risberg Pipeline Project Nears Completion
Source: Star Beacon Originally Posted on October 10th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE — A natural gas pipeline has less than a mile of pipe left to install before the project is finished. The Risberg Pipeline, constructed by RH energytrans, is nearing...
Meadville to Ohio Pipeline Nears Completion
Source: Meadville Tribune Originally Posted on October 9th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE, Ohio — A Meadville-to-Ohio natural gas pipeline has less than a mile of pipe left to install before the project is finished. The Risberg Pipeline, constructed by RH...
Growth Partnership Celebrates the Best of the County
This is an excerpt from an article written by the Gazette Newspapers, originally posted on September 20th, 2019. You may view the full article HERE Growth Partnership Executive Director Greg Myers presented the Infrastructure Transformation Award to RH energytrans,...
Risberg Pipeline Targets Mid-Fall for Completion Date
Source: Star Beacon Originally Posted on September 4th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE — The Risberg natural gas pipeline is expected to be finished by mid-fall of this year. The $86 million natural gas pipeline will run from Meadville, Pa., to North...
Erie-Ohio Pipeline Project Nears Completion
Source: GoErie.com Originally Posted on July 31st, 2019 by JIM MARTIN NORTH KINGSVILLE, Ohio — Forty-foot sections of 12-inch steel pipe — a pipe so large you could roll a basketball down the inside — lay in sections along Route 20 last week. These pipes, which will...
Work Continues along Route 20 on Risberg Pipeline
Source: Star Beacon Originally Posted on July 31st, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE — Work continues on the Risberg natural gas pipeline, with new stretches of pipe being laid out along the north side of Route 20 in North Kingsville. The $86 million pipeline...
Work Continues on Gas Pipeline
Source: Star Beacon Originally Posted on July 6th, 2019 by BRIAN HAYTCHER NORTH KINGSVILLE — Work is continuing on the Risberg Pipeline, as it moves deeper into Ohio. The Risberg Pipeline, first announced in 2017, connects an existing pipeline in Meadville,...
Filings
Certificate of Compliance Report No. 64 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 63 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 62 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 61 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 60 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 59 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 58 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 57 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 56 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 53 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Certificate of Compliance Report No. 52 Submitted in FERC CP18-06-000 by RH energytrans, LLC, et al.
On December 7, 2018, the Federal Energy Regulatory Commission issued an order granting a Certificate of Public Convenience and Necessity to RH energytrans, LLC (“RH”) for the Risberg Line Project in the above-identified docket. On December 12, 2018, RH submitted its...
Docket No. CP18-6-000 Request for Extension of Time
Letter order granting RH energytrans, LLC’s 10/19/2020 request for a two-year extension of time until 12/07/2022, to complete construction and place into service its Meadville and Countyline compressor stations under CP18-6.